ARMIDE works update – 23rd October 2017

ARMIDE works update – 23rd October 2017

Photos of recent works undertaken

  • Helm area mock-up – to be finalised

  • Laminating the bow thruster tunnel into place

  • Helm area mock-up with doghouse mock-up in background

  • First dry fit of bow thruster motor with curing internal laminates

  • Patternmaking for the hawse pipes; one pattern will do for both sides

  • Bulwark mock-up to gain correct angles for hawse pipes (ply ellipse on bulwark)

  • Ply mock-up of arch-board around stern of yacht also giving shape of upper section of transom

  • Restored forehatch ready for staining and varnishing

  • Stain samples to help select correct colouring prior to varnishing of old timber

  • Ply mock-up of arch-board around stern of yacht including upper section of transom

  • Oregon pine bowsprit being rounded off

  • Restored forehatch lid with new teak strakes

  • Rigging screw samples.

  • Marking out forward end of teak deck onto plywood sub-deck with king plank width in blue tape

Marking out forward end of teak deck onto plywood sub-deck with king plank width in blue tape
Rigging screw samples.