Armide report December 17th 2018
Armide report December 17th 2018
A classic is reborn
Armide report December 17th 2018
Armide report December 10th 2018
Armide report December 3rd 2018
Armide report Nov 26th 2018
Armide report Nov 19th 2018
Armide report Nov 12th 2018
Armide report Nov 5th 2018
Armide report Oct 29th 2018
Armide report Oct 22nd 2018
Armide report Oct 15th 2018
Armide report Oct 10th 2018
Armide report Oct 1st 2018
Armide report Sept 24th 2018
Armide report Sept 17th 2018
Armide report Sept 10th 2018
Armide report Sept 3rd 2018
Armide report July 30th 2018
Armide report July 23rd 2018
Armide report July 16th 2018
Armide report July 9th 2018
Armide report July 2nd 2018
Armide report June 25th 2018
Armide report June 18th 2018
Armide report June 11th 2018
Armide report June 4th 2018
Armide report May 28st 2018
Armide report May 21st 2018
Armide report May 14th 2018
Armide report May 7th 2018
Armide report April 30th 2018
Armide report April 23rd 2018
Armide report April 16th 2018
Armide report April 9th 2018
Armide report April 4th 2018
Armide report March 26th
Armide report March 19th 2018
Armide report March 12th 2018
Armide report March 5th 2018
Armide report February 26th 2018
Armide report February 20th 2018 THE DOGHOUSE The original doghouse on Armide is thought to have been built from the wood Niangon that comes from the Ivory Coast and Ghana. The structure and surrounding deck were in a very poor condition when the yacht arrived at Classic Works, particularly at Read More
Armide report February 12th 2018 FAIRING BATTENS FOR THE SHEERLINE Two deep plywood battens have been temporarily clamped either side of the deck on the wooden stanchions in order to finalise the sheer-line. A deep batten is necessary because it is not possible to stand back and see the sheer-line Read More
Armide report February 5th 2018
Armide report January 29th 2018
Armide report January 15th 2018
Armide report January 15th 2018
Armide report January 8th 2018
Armide report January 2nd 2018
Armide report December 18th 2017
Armide report December 11th 2017
Armide report December 4th 2017
ARMIDE works update – 27th November 2017
ARMIDE works update – 20th November 2017
ARMIDE works update – 13th November 2017
ARMIDE works update – 6th November 2017
Pictures
ARMIDE works update – 30th October 2017
ARMIDE works update – 23rd October 2017
ARMIDE works update – 16th October 2017
ARMIDE works update – 9th October 2017
ARMIDE works update – 18th September 2017
ARMIDE works update – early September 2017
THE STEAM BENT FRAMES THE WOODEN FLOORS
ARMIDE works update – early August 2017
ARMIDE REPORT AND MEETING NOTES July 17th 2017
ARMIDE REPORT AND MEETING NOTES July 10th 2017
INTRODUCTION
CLASSIC WORKS – patterns for Armide hull and deck fittings
ARMIDE REPORT AND MEETING NOTES June 27th 2017
ARMIDE – Skylights report June 15th 2017
MEETING NOTES
Armide works photo report May 2017
Armide works photo report April 2017
Armide works photo report Mar 2017
Armide works photo report Feb 2017
Armide works photo report Jan 2017
Armide works photo report Dec 2016
Armide works photo report Nov 2016.
ARMIDE works update – end October 2016
ARMIDE works update – end September 2016
ARMIDE works update – end August 2016
ARMIDE works update – end July 2016
ARMIDE works update – end June 2016
ARMIDE works update – end May 2016
ARMIDE works update – end March 2016